denis_ireri c515066403 Add Roll Genealogy and Work Order Cost Variance reports
- Roll Genealogy traces a batch backward (what went into it) or forward
  (where it was used) through submitted Manufacture entries, showing roll
  dimensions and the latest inspection disposition at each step (B3).
- Work Order Cost Variance compares BOM-planned material, operating cost and
  scrap with actual consumption and Job Card time, plus recorded waste kg (M5).